That minor variance application D20-2021-004 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act.
Conditions:
1) That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C submitted as part of Report COA2021-009, which shall be attached to and form part of the Committee’s Decision; and
2) That the building construction related to the minor variances shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection.
This approval pertains to the application as described in report COA2021-009. Fulfillment of all conditions is required for the Minor Variances to be considered final and binding.