Cell 4 and 5 north construction is still ongoing. The cell is complete but still has small items to be finalized prior to completion.
The rehab transfer station project has been started. The contractor has removed the back wall and door and are currently pouring concrete with hopes of utilizing the building by August. Recycling has temporarily been placed in the construction and demolition bunker as well as at the back of the building.
The scales and drop off area's new design is still in process but is anticipated to be completed by Q3 in 2025.
Sludge removal from storm water retention ponds A and B has been completed. All the valves are operational and the project has been closed.
Engineering is continuing to work on the environmental assessment (EA). There are no updates at this time.