Chair Robertson called the meeting to order at 1:00pm. 

Chair Robertson, and Members S. Strangway, B. Archer, S. Richardson and J. Robinson were in attendance in person.

Councillor Yeo attended via electronic participation.

Staff, L. Barrie, Manager of Planning, M. LaHay, Secretary-Treasurer, C. Crockford, Recording Secretary and K. Evans, Planner II attended in person.

Staff, Susanne Murchison, Chief Building Official attended via electronic participation.

Absent: D. Marsh

September 22, 2022
Committee of Adjustment Agenda

  • CA2022-095
    Moved ByB. Archer
    Seconded ByS. Richardson

    That the agenda for September 22, 2022 meeting be approved as printed.

    Carried

There were no declarations of pecuniary interest disclosed.

August 18, 2022
Committee of Adjustment Minutes

  • CA2022-096
    Moved ByJ. Robinson
    Seconded ByS. Strangway

    That the minutes of the previous meeting held August 18, 2022 be adopted as printed.

    Carried

Leah Barrie, Manager of Planning
File Number: D20-2022-056
Location: 28 Treewood Lane
Part Lot 1, West Bay Range (being Lot 4 and Part Block D, Plan 175)
Geographic Township of Bexley
Owner: Stephanie Lange

Ms. Barrie summarized Report COA2022-065. The purpose and effect is to facilitate replacement of a residential dwelling. Section 12.2.1.3 of the By-law requires a minimum water setback of 15 metres; the existing reduced setbacks of +/- 13 metres (dwelling) and +/- 10.13 metres (deck) are proposed to remain.

There were no concerns from the public or agencies.

The applicant, Ms. Lange was present via electronic participation.

Question raised by the Committee to the applicant:

1) How will the deck be accessed if the stairs are being removed? Ms. Lange responded.

There were no further questions from the Committee or other persons.

  • CA2022-097
    Moved ByS. Strangway
    Seconded ByS. Richardson

    That minor variance application D20-2022-056 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act.

    Conditions

    1)    That building construction related to this approval shall proceed generally in accordance with the sketch in Appendix C and D submitted as part of Report COA2022-065, which shall be attached to and form part of the Committee’s Decision; and,

    2)    That building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection.

    This approval pertains to the application as described in report COA2022-065. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.

    Carried

Leah Barrie, Manager of Planning
File Number: D20-2022-058
Location: 95 Lakeview Cottage Road
Lot 38, Plan 179
Geographic Township of Bexley
Owners: Maureen Harradine and Victoria Dyment
Applicant: Colin Darling

Ms. Barrie summarized Report COA2022-066. The purpose and effect is to facilitate a second storey residential addition. Section 12.2.1.3 of the By-law requires a minimum water setback of 15 metres; the existing reduced setbacks of +/- 11.54 metres (dwelling) and +/- 8.26 metres (deck) are proposed to remain.

There were no concerns from the public or agencies.

Questions raised by the Committee:

1) The Committee referred to past applications whereby a condition was included to make sure a structure be removed. As there is not a condition included in this application who will be responsible to make sure they comply? Ms. Murchison responded that it would be dealt with through the Building Permit Process.

Ms. Barrie spoke to the Building and Septic, Part 8 Sewage System comments. The Supervisor of Part 8 Sewage Systems reviewed the proposal noting the additional space as a result of the second floor addition will add to the capacity of the sewage system. The existing sewage system does not have the capacity to proceed with the current proposal. A third condition has been included of which the owner is aware.

2) Does the property have sufficient space on the lot for a Class 4 system? Ms. Barrie responded yes.

The applicant, Mr. Darling was present via electronic participation. Clarification was provided regarding the storage shed. Although the shed does not require to be removed to comply with the zoning by-law, the owner has elected to remove it. Mr. Darling confirmed he is aware and agreed to the condition to include a Class 4 Sewage System.

  • CA2022-098
    Moved ByB. Archer
    Seconded ByCouncillor Yeo

    That minor variance application D20-2022-058 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act.

    Conditions

    1)    That building construction related to this approval shall proceed generally in accordance with the sketch in Appendix C and D submitted as part of Report COA2022-066, which shall be attached to and form part of the Committee’s Decision; and,

    2)    That building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection; and,

    3)    That building construction related to this approval shall proceed provided the Supervisor – Part 8 Sewage Systems is satisfied that a Class 4 Sewage System can be accommodated on the property, in compliance with the Ontario Building Code, to service the dwelling.

    This approval pertains to the application as described in report COA2022-066. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.

    Carried

Leah Barrie, Manager of Planning
File Number: D20-2022-059
Location: 32 Leslie Frost Lane
Part Lot 7, Concession 9 (being Lot 15, Plan 143)
Geographic Township of Fenelon
Owner: Drew Coombs
Applicant: Garry Newhook

Ms. Barrie summarized Report COA2022-067. The purpose and effect is to facilitate replacement of a former detached accessory building (garage). Section 3.1.2.4 of the By-law requires a minimum front yard setback of 7.5 metres; the former existing reduced setback of +/- 4.8 metres is proposed.

There were no concerns received from agencies.

Ms. Barrie indicated there were two public concerns from Mr. Ferguson of 36 Leslie Frost Lane and Mr. and Mrs. Flett of 30 Leslie Frost Lane.

Concerns:

1) Property used as Airbnb or Short Term rental.
2) Numerous cars parked on the property causing constraints.
3) Garage - Potential to convert to habitable space in the future.
4) Shed missing from the site plan.
5) Proposed garage too large and may decrease the value of neighbouring properties.
6) Concerns if application approved will set a precedent.
7) There are 4 buildings on the property not three.

Ms. Barrie summarized a submission by the owner in response to the neighbours concerns.

Questions raised by the Committee:

1) Reference appendix D showing a side view of a set of stairs to a landing. Is the floor additional storage space? Ms. Barrie responded.
2) Is access to the second floor level within the garage? Ms. Barrie provided a response.

The applicant, Mr. Newhook was present via electronic participation. Mr. Newhook clarified there is loft space in the garage. The garage has enough space for a car with storage space above and not for habitation. He also spoke to the neighbours concerns.

The owner, Mr. Coombs was present via electronic participation. Mr. Coombs spoke to the neighbours concerns.

In opposition, Mr. Flett was present via electronic participation and stated his concerns with short term rentals and the size of the garage. Mr. Flett’s submission was previously circulated to the Committee.

The Committee asked for confirmation from Mr. Flett if Mr. Coombs has advertised rentals online. Mr. Flett replied yes.

Mr. Coombs spoke to the nature of rentals that took place in the past 6 years.

Questions raised by the Committee:
 
1) Is the shed used as a Bunkie or is it intended to be in the future? Mr. Coombs responded.

2) Does a Bunkie require septic and washroom facilities? Ms. Murchison replied the Ontario Building Code looks at three criteria; Square footage of living space, number of bedrooms and number of plumbing fixtures. If a previously constructed shed or garage is converted to a Bunkie and deemed living space, a change of use permit is required and evaluation of the building is required to see if the sewage system can accommodate the additional living space.

3) Can a property owner convert a shed to a Bunkie without washroom facilities? Ms. Murchison provided a response.

4) The Committee noted that there are two issues which are not related to the application being brought before the Committee. The Chair responded the reason for the discussion is because it was part of a public submission with concerns which need to be addressed.

5) Clarification from the Planner that the application is before the Committee because the proposed garage is too close to the front lot line. If the owner was to build to the required front yard setback, it wouldn't need to be brought before the Committee. Is that correct? Ms. Barrie replied.

No further questions from the Committee or other persons.

  • CA2022-099
    Moved ByS. Strangway
    Seconded ByJ. Robinson

    That minor variance application D20-2022-059 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act.

    Conditions

    1)    That building construction related to this approval shall proceed generally in accordance with the sketch in Appendix C and D submitted as part of Report COA2022-067, which shall be attached to and form part of the Committee’s Decision; and,

    2)    That building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection.

    This approval pertains to the application as described in report COA2022-067. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.

    Carried

Leah Barrie, Manager of Planning
File Number: D20-2022-060
Location: 138 Shrike Road
Part Lot 3, Concession 9
Geographic Township of Carden
Owner: Irwin Kandelsdorfer

Ms. Barrie summarized Report COA2022-068. The purpose and effect is to facilitate a new dwelling. The existing dwelling is proposed to be converted into an accessory building. Section 14.1.b. of the By-law permits accessory buildings in side or rear yards only; the existing building is in the front yard. A second accessory building (shipping container) is also located in the front yard. Section 7.2.c. requires a minimum front yard setback of 30 metres; the existing setback is +/- 21.6 metres.

No concerns or issues from the public and agencies.

Questions raised by the Committee:

1) Are there rules and regulations for the placement of shipping containers? Ms. Barrie and Ms. Murchison provided a response.

2) How many accessory structures are permitted on a property? Ms. Barrie asked the Chair for the opportunity to review the provisions for the Carden Zoning by-law.

The Chair called for a break at 2:24pm to allow Ms. Barrie time to review the Carden Zoning by-law. The Chair called the meeting to order at 2:30pm.

Ms. Barrie noted that in the Carden Zoning by-law, accessory structures are not measured by number of structures but a percentage of the lot, in this case 8% of a 100 acre lot.

The agent acting on behalf of the applicant, Mr. Leblanc was present via electronic participation and spoke to the Committee.

Member Archer noted that she was opposed to the second relief sought and proposed that the shipping container be moved to the rear of the dwelling from the front yard.

No further questions from the Committee or other persons.

  • Moved ByCouncillor Yeo
    Seconded ByS. Strangway

    That minor variance application D20-2022-060 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act.

    Conditions

    1)    That building construction related to this approval shall proceed generally in accordance with the sketch in Appendix C and D submitted as part of Report COA2022-068, which shall be attached to and form part of the Committee’s Decision; and,

    2)    That building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection.

    This approval pertains to the application as described in report COA2022-068. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.

  • Moved ByB. Archer
    Seconded ByJ. Robinson

    That the motion be amended so that the relief sought in section 1 'that the accessory building only pertained to the initial dwelling and that the relief sought in section 2', be removed.

    Carried
  • The Original Motion was put back on the floor as amended.

    CA2022-100
    Moved ByCouncillor Yeo
    Seconded ByS. Strangway

    That minor variance application D20-2022-060 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act.

    Conditions

    1) That building construction related to this approval shall proceed generally in accordance with the sketch in Appendix C and D submitted as part of Report COA2022-068, which shall be attached to and form part of the Committee’s Decision; and,

    2) That building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection.

    This approval pertains to the application as described in report COA2022-068. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.

    Carried

Leah Barrie, Manager of Planning
File Number: D20-2022-061
Location: 14 Cornwall Street
Part Lot 9, Concession 4 (being Lot 8, Plan 537)
Geographic Township of Emily
Owners: James and Constance Ellison

Ms. Barrie summarized Report COA2022-069. The purpose and effect is to facilitate a residential addition. Section 11.2.1.3(b) of the By-law requires a minimum interior side yard setback of 3 metres; the proposed setback is +/- 1.25 metres.

Ms. Barrie noted that a public submission was received from Ms. Mitchell of 16 Cornwall Street with a concern to additional water drainage.

The applicant, Mr. Ellison was present via electronic participation and available for questions.

Question raised by the Committee:

1) Will there be any tree removal due to the addition? Mr. Ellison responded.

There were no further questions from the Committee or other persons.

  • CA2022-101
    Moved ByJ. Robinson
    Seconded ByCouncillor Yeo

    That minor variance application D20-2022-061 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act.

    Conditions

    1)    That building construction related to this approval shall proceed generally in accordance with the sketch in Appendix C and D submitted as part of Report COA2022-069, which shall be attached to and form part of the Committee’s Decision; and,

    2)    That building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection; and,

    3)    That building construction related to this approval shall proceed provided the Supervisor – Part 8 Sewage Systems is satisfied that the Class 4 Sewage System existing on the property can accommodate the proposal and will be in compliance with the Ontario Building Code or any predecessor legislation.

    This approval pertains to the application as described in report COA2022-069. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.

    Carried

Leah Barrie, Manager of Planning
File Number: D20-2022-062
Location: 232 Glenarm Road
Part Lot 10, Concession 2 (being Part 1, RP 57R404)
Geographic Township of Eldon
Owner: Charles Poley
Applicant: Geoff Graves

Ms. Barrie summarized Report COA2022-070. The purpose and effect is to facilitate the enlargement of the legal non-conforming single detached dwelling (est. 1974), whereby its residential use predates the Zoning By-law adopted in 1994, that zones the lot General Industrial ‘M2’, and Section 18.1 does not otherwise permit residential uses.

Ms. Barrie noted that there were no concerns received from the public or agencies.

The applicant, Mr. Graves was present via electronic participation.

There were no questions from the Committee or other persons.

  • CA2022-102
    Moved ByS. Richardson
    Seconded ByS. Strangway

    That minor variance application D20-2022-062 be GRANTED, as the application satisfies Section 45(2) of the Planning Act.

    Conditions

    1)    That building construction related to this approval shall proceed generally in accordance with the sketch in Appendix C and D submitted as part of Report COA2022-070, which shall be attached to and form part of the Committee’s Decision; and,

    2)    That building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection.

    This approval pertains to the application as described in report COA2022-070. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.

    Carried

Leah Barrie, Manager of Planning
File Number: D20-2022-063
Location: 49 Cedar Road
Part Lot 19, Concession 6 (being Lot 7, Plan 431)
Geographic Township of Somerville
Owners: Colin and Cindy Chisholm

 

Ms. Barrie summarized Report COA2022-071. The purpose and effect is to facilitate a deck addition. Section 5.2.f. of the By-law requires a minimum water setback of 15 metres; the existing reduced setback is +/- 11.6 metres (deck), proposed to remain for the deck addition, and with a further encroachment for the stairs at +/- 10.7 metres.

Ms. Barrie noted that there were no concerns or objections from the public or agencies.

Question raised by the Committee:

1) Clarification as to the direction of the deck addition? Ms. Barrie provided a response.

The applicant, Ms. Chisholm was present via electronic participation and available for questions.

No further questions from the Committee or other persons.

  • CA2022-103
    Moved ByB. Archer
    Seconded ByS. Richardson

    That minor variance application D20-2022-063 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act.

    Conditions

    1)    That building construction related to this approval shall proceed generally in accordance with the sketch in Appendix C and D submitted as part of Report COA2022-071, which shall be attached to and form part of the Committee’s Decision; and,

    2)    That building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection.

    This approval pertains to the application as described in report COA2022-071. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.

    Carried

Leah Barrie, Manager of Planning
File Number: D20-2022-064
Location: 10 Leaf Street
Lot 7, Plan 234
Geographic Township of Fenelon
Owners: Kevin Decooman and Doreen MacPherson

Ms. Barrie summarized the memorandum included in the Members report packages and recommended a deferral to allow further evaluation and discussion amongst the Planning, Building and Septic staff together with the owners.

The Committee agreed the application be deferred to a subsequent meeting scheduled for December 1, 2022 or sooner pending outcome of inspection.

Councillor Yeo left the meeting at 3:06pm.

  • CA2022-104
    Moved ByJ. Robinson
    Seconded ByS. Strangway

    That Minor Variance Application D20-2022-064 be deferred for a period of not more than two months, returning at the latest to the December 1, 2022 meeting.

    Carried

Leah Barrie, Manager of Planning
File Number: D20-2022-065
Location: 63 Charlore Park Drive
Part Lot 14, Concession 7 (being Part 1, RP 57R9126)
Geographic Township of Emily
Owners: Daniel and Shauna Keeler

Ms. Barrie brought to the Committee's attention the Planning Act requirements for circulating notice. The reason being is that the sign to be posted on the property was prepared but not picked up and posted due to a clerical error. As a result of the circulation no concerns or issues were received from the public or agencies. However, staff felt that sufficient notice was given via the 60 metre circulation mailed to surrounding neighbours and the notice advertised on the City's website. The Committee took a vote in favour to continue with the application which was carried.

Ms. Barrie summarized Report COA2022-073. The purpose and effect is to facilitate construction of a detached accessory building (workshop/garage). Section 3.1.2.2 provides that an accessory building may be erected no closer to a street than the required front yard setback for the zone in which it is located, that being 7.5 metres; the proposed setback is +/- 5.5 metres.

The Committee raised the following questions:

1) Appendix C, location of second driveway? Ms. Barrie provided a response.

2) Is the setback sought behind the garage to the lot line? Ms. Barrie responded.

3) Can a condition to obtain a permit for the additional driveway be added? Ms. Barrie agreed.

The applicants, Mr. and Mrs. Keeler were not present.

There were no further questions from the Committee or other persons.

The application was granted approval as amended.

  • CA2022-105
    Moved ByS. Strangway
    Seconded ByB. Archer

    That minor variance application D20-2022-065 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act.

    Conditions

    1)    That building construction related to this approval shall proceed generally in accordance with the sketch in Appendix C submitted as part of Report COA2022-073, which shall be attached to and form part of the Committee’s Decision; and,

    2)    That building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection.

    3)    That building construction related to this approval shall proceed provided the owner obtains an entrance permit for the additional driveway intended to serve the proposed detached accessory building (workshop/garage).

    This approval pertains to the application as described in report COA2022-073. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.

    Carried

Leah Barrie, Manager of Planning
File Number: D20-2021-029
Location: Vacant land, Unassumed Road Allowance
Part of Lot 16 and 17, Concession 10
Geographic Township of Somerville
Owner: Steven Harjula

Ms. Barrie summarized the recommendation for deferral at the August 18, 2022 Committee of Adjustment meeting to allow the owner and the Committee time to review the Council Policy CP2017-010, Assumption of Private and Unassumed Roads Policy. The Report COA2022-064 was prepared however not presented and noted that the information within the report had not changed. Ms. Barrie also spoke to the Management Directive. The purpose and effect is to facilitate construction of a new dwelling and agricultural building in support of a nursery business on a lot absent frontage on an improved public street. Section 18.8.1 provides that no building or structure shall be erected in any zone unless the lot upon which such building or structure is to be erected has a lot line which abuts an improved public street, where access can be obtained off such street; the existing lot abuts a municipal unassumed road.

Questions raised by the Committee:

1) Clarification that the recommendation put forward is the original report? Ms. Barrie provided a response.

2) If the Committee approve the recommendation will this allow the applicant to obtain a building permit to build a dwelling and accessory building to house the trees and in two years then enter in to a license agreement with the City to construct a road at the owner’s expense? Ms. Barrie responded that the proponent will first submit a proposal which will define how they will achieve compliance with the Council Policy and then be eligible for a building permit.

3) Concerns to time lines. Ms. Barrie suggested that the owner speak to his priorities.
Discussions ensued.

The applicant, Mr. Harjula was present via electronic participation and spoke to the Committee.

No further questions from the Committee or other persons.

  • CA2022-106
    Moved ByS. Strangway
    Seconded ByS. Richardson

    That minor variance application D20-2021-029 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act.

    Conditions

    1)    That the owner submit to the City a proposal to assume the unnamed road by service, in accordance with Council Policy CP2017-010 within twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon receipt of the proposal.

    This approval pertains to the application as described in report COA2022-064. Fulfillment of all conditions is required for the Minor Variances to be considered final and binding.

    Carried

The next meeting will be Thursday, October 27th at 1:00pm in Council Chambers, City Hall.

  • CA2022-107
    Moved ByB. Archer
    Seconded ByJ. Robinson

    That the meeting be adjourned at 4:12pm.

    Carried